Duration7 months

Project Value€1,200,000

Description of Works

The Rivierstaete building is a 10 story (including plant rooms) structure which was constructed in the early 1970’s.

The building stands at 36000m2 and was in use until 2012, as the largest office space structure in Europe.

Vastint (InterIkea) purchased the property 2014 with plans to retain the structure but completely remodel the internal and external elements.

HDR were contracted as principal contractor By Vastint BV to carry out the internal demolition of all non-structural elements and the removal of all asbestos containing materials.

The project was challenging due to the tight programme and the added complication that both Dutch and UK legislation had to be adhered to.

To find out more call us now on 01789 540080

Rivierstaete Amsteldijk
Arial Image

Rivierstaete Amsteldijk
Typical office floor prior to demolition and asbestos removal.

Rivierstaete Amsteldijk
All floors had convector radiator running the whole perimeter which were heavily contaminated with fiberous asbestos containing materials.

Rivierstaete Amsteldijk
Typical floor plate following our works cleared of all non-load baring walls, partitions fixtures & fittings and stripped of all asbestos containing materials.

Rivierstaete Amsteldijk